Question 1
Interpret Figures Q1.1 to Q1.7 and apply measurement techniques to the following questions.
Specification Notes for Question 1:
Reinforced concrete shall be grade 40. Lean concrete shall be grade 15.
Formwork shall be of sawn timber for sub-structure works and written timber for super-structure works.
The concrete cover shall be 50 mm thick for sub-structure works and 25 mm for super-structure works.
Topsoil excavation shall be to a reduced level and deposited on-site in temporary spoil heaps average of 30m away from the excavation works for reuse.
Reinforcement for roof beams and roof slab is not to be measured.
Question 1a
Prepare a take-off list, and unit of measurement and apply relevant SMM clauses for measuring the reinforced concrete structure.
Question 1b
Take off quantities for the sub-structure works.
Question 1c
Take off quantities for the super-structure works.
Question 1d
Take off quantities for the reinforcement works.
The post QSM301: Prepare a take-off list, and unit of measurement and apply relevant SMM clauses for measuring the reinforced: Construction Measurement (3 of 4) Advanced Civil & Structural Works Assignment, SUSS appeared first on Singapore Assignment Help.