PMG640 – Project Scheduling and Cost Planning

Due Date:  Sunday by 11:59pm 

Total Points: 100

 Instructions: 

•        Update your project file based on any feedback given last week. If assignment is not correctly updated, then points will be deducted.

•        Add Project Management Processes to your WBS if you have not already done so. This will need to include the PM processes that would be consistent with the planning, executing, controlling, and closing activities. o You will need to create appropriate deliverables (adjective / noun format) o You will need to create appropriate activities (action verb / adjective / noun format)

o   Sequence the activities

o   You will need to estimate times (be sure to differentiate between duration & effort / work)

•       

Sequence all your activities using the predecessors’ column, creating a closed network diagram (please see multimedia video showing you how to ensure you have a closed network diagram). At least 4 of your tasks relationships must be different than Finish to Start (insert a note on these tasks to explain the task relationship that you chose); remember, you should create a closed network diagram

•        Add lead time to at least 2 task relationships with explanatory note

•        Add lag time to at least 1 task relationship with explanatory note

•        Add a constraint to at least 2 tasks and provide a note explaining why the task is constrained (make certain that the constraint does not create a conflict in the project schedule)

•        View your critical path

•        Create a note in Line 1 of your MS Project file where you tell me what tasks are on the critical path. It must be in this location. Be sure you tell me the correct critical path, which may or may not be the tasks highlighted in MS Project.

•        Display your project in Network Diagram view and save it so that it opens automatically in this view

Requirements:

 

•        Use MS Project to complete your assignment.

•        Save your files using the following filename convention: 

o   MSProject2 – FirstName_LastName

 

Be sure to read the criteria, by which your paper/project will be evaluated, before you write, and again after you write.

Evaluation Rubric for Unit 3: MS Project #2 Assignment

 

CRITERIA

Deficient

 

Needs Improvement

Proficient

 

Exemplary

 

 

0 – 15 Points

16 – 19 Points

20 – 24 Points

25 Points

Work

Breakdown

Structure

Work
Packages are not fully decomposed but less than the 30 Activities necessary
to create the deliverables. Some of the correct naming conventions are
missing.

Work
Packages are fully decomposed but less than the 40 Activities necessary to
create the deliverables. Some of the correct naming conventions are missing.

Work
Packages are fully decomposed into the 40 Activities necessary to create the
deliverables. Some of the correct naming conventions are missing

Work Packages are fully
decomposed into the 40

Activities
necessary to create the deliverables. Correct naming conventions are used.

Sequence

Activities

All
activities are

Sequenced
using the predecessors’ column without a closed network diagram. At least 1-2
of your tasks relationships must be different than Finish to Start.

All
activities are

Sequenced
using the predecessors’ column without a closed network diagram. At least 3
of your tasks relationships must be different than Finish to Start.

All
activities are

Sequenced
using the predecessors’ column with a closed network diagram. At least 3 of
your tasks relationships must be different than Finish to

Start

All
activities are Sequenced using the predecessors’ column with a closed network
diagram. At least 4 of your tasks relationships must be different than Finish
to Start 

Lead
& Lag

Includes
a lead time to

at least 1 task
relationships with no clear explanatory note and a  lag time to at least 1 task relationship
with no explanatory note

 

Includes
a lead time to

at least 1 task
relationships with no clear explanatory note and a  lag time to at least 1 task relationship
with explanatory note

 

Includes
a lead time to

at least 2 task
relationships with no clear explanatory note and a  lag time to at least 1 task relationship
with explanatory note

 

Includes a lead
time to at least 2 task relationships with explanatory note and a  lag time to at least 1 task relationship
with explanatory note

 

 

0 – 15 Points

16 – 17 Points

18 – 19 Points

20 Points

Critical
Path

Critical Path is not
identified and some of the activities on the critical path are clear but not
highlighted.

 

Critical Path is
identified and some of the activities on the critical path are clear but not
highlighted.

 

Critical Path is
identified and all activities on the critical path are clear but not
highlighted.

 

 

 

 

 

 

Critical Path is
identified and all activities on the critical path are clear and highlighted.
 

 

 

0  Points

1 – 2 Points

3 – 4 Points

5 Points

Clear and

Professional

Writing 

Writing assignment
contains no sense of organization.

Paragraphs
lack clear ideas.

Contains several
errors in grammar, spelling and punctuation which detracts from content of
the passage.

 

Writing
assignment contains a sense of organization. Some paragraphs have clear
ideas. Contains several minor errors in grammar, spelling and punctuation,
but does not detract from content of the passage.

Writing
assignment contains good overall organization. Most paragraphs have clear
ideas and are supported with some examples. Mostly free of errors in grammar,
spelling and punctuation.

Writing
assignment is well-planned and well-thought out. All paragraphs have clear
ideas, are supported with examples and have smooth transitions.   Free of errors in grammar, spelling and
punctuation.

 

 

 

Copyright Statement

Post University’s courses contain copyrighted resources created by the University, licensed from various third parties, or unless otherwise noted. In compliance with U.S. Copyright Law, these resources may not be reproduced, revised, or distributed without the written permission of Post University.  Students found to be in violation of this policy are subject to civil and criminal liabilities associated with the Federal Copyright Act and risk dismissal from the university under the Academic Dishonesty policy.  Unless otherwise noted, access to these materials is limited to the duration of the course.  Students should contact the library (library@post.edu) for information on which resources can be printed.